Description

Tseung Kwan O – Lam Tin Tunnel – Road P2/D4 and Associated Works mainly comprise construction of a section of Road P2 in TKO Town Centre, modification of the existing road junction at Po Yap Road/ Po Shun Road/ Chui Ling Road and construction of a grade separated footbridge cum cycle track.

Contract No. NE/2017/02
Scope
  • Construction of a section of Road P2 in TKO Town Centre;
  • Modification of the existing road junction at Po Yap Road/Po Shun Road/Chui Ling Road into a signalised junction;
  • Construction of a grade seprated footbridge cum cycle track (namely the Southern Footbridge with provision of lifts; and
  • Junction Improvement at Po Yap Road/Tong Yin Street.
Commencement Date
30 November 2017
Tentative Completion Date 2022
Contract Sum $257 million
Consultant AECOM Asia Company Limited
Contractor Zhen Hua Engineering Company Limited



Site Plan




Works Progress / What's New

February 2024

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

January 2024

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

December 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

November 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

October 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

September 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

August 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

July 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

June 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

May 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

April 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

March 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

February 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

January 2023

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

December 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

November 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

October 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

September 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

August 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

July 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

June 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

May 2022

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

April 2022

AERIAL PHOTO OF WORKSITE

GENERAL VIEW OF WORKSITE

March 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

February 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

January 2022

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

December 2021

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

November 2021

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

October 2021

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

September 2021

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

August 2021

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

July 2021

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

June 2021

AERIAL PHOTO OF WORKSITE

FOOTPATH AND CYCLE TRACK AT PO YAP ROAD

May 2021

AERIAL PHOTO OF WORKSITE

PIER AND LIFT SHAFT CONSTRUCTION FOR SOUTHERN FOOTBRIDGE IN PROGRES

April 2021

AERIAL PHOTO OF WORKSITE

ROAD WIDENING OF PO YAP ROAD

March 2021

AERIAL PHOTO OF WORKSITE

CONSTRUCTION OF SOUTHERN FOOTBRIDGE IN PROGRESS

ROAD WIDENING OF PO YAP ROAD

February 2021

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

CONSTRUCTION OF SOUTHERN FOOTBRIDGE IN PROGRESS

January 2021

AERIAL PHOTO OF WORKSITE

AERIAL PHOTO OF WORKSITE

December 2020

AERIAL PHOTO OF WORKSITE

November 2020

AERIAL PHOTO OF WORKSITE

PIER AND STAIRCASE CONSTRUCTION FOR SOUTHERN FOOTBRIDGE IN PROGRESS

October 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

PIER AND STAIRCASE CONSTRUCTION FOR SOUTHERN FOOTBRIDGE IN PROGRESS

September 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

August 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

PIER AND STAIRCASE CONSTRUCTION FOR SOUTHERN FOOTBRIDGE IN PROGRESS

July 2020

AERIAL PHOTO OF WORKSITE

PIER CONSTRUCTION IN PROGRESS

June 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

PIER AND LIFT SHAFT CONSTRUCTION FOR SOUTHERN FOOTBRIDGE IN PROGRESS

May 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

April 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

March 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

February 2020

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

ROAD CONSTRUCTION WORKS IN PROGRESS

January 2020

AERIAL PHOTO OF WORKSITE

BORED PILE CONSTRUCTION IN PROGRESS

December 2019

BORED PILE CONSTRUCTION IN PROGRESS

PILE CAP CONSTRUCTION IN PROGRESS

November 2019

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

October 2019

AERIAL PHOTO OF WORKSITE

ROAD CONSTRUCTION WORKS IN PROGRESS

September 2019

AERIAL PHOTO OF WORKSITE

BORED PILE CONSTRUCTION IN PROGRESS

August 2019

AERIAL PHOTO OF WORKSITE

CONCRETING OF BORED PILE IN PROGRESS

July 2019

AERIAL PHOTO OF WORKSITE

BORED PILE CONSTRUCTION IN PROGRESS

June 2019

AERIAL PHOTO OF WORKSITE

BORED PILE CONSTRUCTION IN PROGRESS

May 2019

AERIAL PHOTO OF WORKSITE

BORED PILE CONSTRUCTION IN PROGRESS

February 2019

AERIAL PHOTO OF WORKSITE

January 2019

AERIAL PHOTO OF WORKSITE

December 2018

AERIAL PHOTO OF WORKSITE

November 2018

AERIAL PHOTO OF WORKSITE

October 2018

AERIAL PHOTO OF WORKSITE

September 2018

AERIAL PHOTO OF WORKSITE

August 2018

AERIAL PHOTO OF WORKSITE

June 2018

AERIAL PHOTO OF WORKSITE

May 2018

AERIAL PHOTO OF WORKSITE

April 2018

AERIAL PHOTO OF WORKSITE

March 2018

AERIAL PHOTO OF WORKSITE

February 2018

GENERAL VIEW OF WORKS AREA

January 2018

GENERAL VIEW OF WORKS AREA

December 2017

GENERAL VIEW OF WORKS AREA




Contact Us

You are welcome to provide your valuable comments to us by the following ways:

Post: 8/F, South Tower, West Kowloon Government Offices, 11 Hoi Ting Road, Yau Ma Tei, Kowloon
Telephone: 5599 7455
Fax: 3910 1600
Email: tkoltt@cedd.gov.hk



Related Links

Civil Engineering and Development Department
Environmental Monitoring and Audit Data and Reports for Tseung Kwan O - Lam Tin Tunnel Project
Tseung Kwan O - Lam Tin Tunnel